One-Person Construction Layout With a Robotic Total Station

One-person construction layout means a single operator lays out points with a robotic total station that tracks the prism pole automatically, while the operator walks the site with the tablet. The instrument does the aiming and measuring; you do the walking and the marking. With good control, clean files and a disciplined setup check, one person can handle anchor bolts, gridlines, sleeves and hangers that used to take a two-person crew.

This guide walks through the workflow we teach on Leica iCON instruments, from file prep to the final back-check. If you are still choosing an instrument, start with our robotic total stations, or rent one for a project first.

What you need for one-person construction layout

  • A robotic total station. Datum's rental fleet covers the iCON robot 50, 60, 70 and 80. The robot 80 comes in iCR82 (2") and iCR85 (5") accuracy versions.
  • A field controller with iCON software. A rugged tablet such as the CC80, CS35 or CC200 running iCON build or iCON site. Some features below, like Auto Staking and Checks, need the iCON build or iCON site Plus level.
  • A prism pole and a 360 prism. Optionally an AP20 AutoPole, which adds automatic pole height, tilt compensation and target identification.
  • Project control you can see from where you plan to set up.
  • Coordinated project files loaded on the tablet.

Step 1: Prepare the files before you mobilize

Most lost layout days start in the office. The iCON tablet works with three file types:

File Format What it is for
Control points .CSV or .TXT Known points for setting up the instrument, usually from the surveyor
Drawings / linework .DWG or .DXF Gridlines and the specific linework you will lay out from
Layout points .CSV or .TXT Defined point locations such as anchor bolts

Strip the drawing down to the project grid and the linework you actually need. Hatches, annotations and extra layers slow the tablet and clutter the map. Then open everything together and confirm that control, linework and points overlay correctly in the same units, orientation and elevations. Survey, GC and trade files often use different coordinate systems. If they do not line up, stop and get the responsible survey or BIM team to resolve it before anyone goes to the field.

Our iCON file import video shows the import steps on the tablet.

Step 2: Set up anywhere and check the geometry

For building layout, the usual method is Setup Anywhere (a resection): put the instrument where it can see both the control and the work area, level it, and measure to two or more known control points. The software calculates the instrument's position and orientation.

  1. Open the Setup app and choose Anywhere.
  2. Level the instrument and enter the instrument height if you need elevations.
  3. Select and measure the control points one at a time, with the correct prism type and height set.
  4. Review the Residuals screen. Deselect any point that is clearly off, rather than accepting a poor solution.

Pay attention to the geometry. iCON grades the setup by the angles between the instrument and each pair of control points; angles between 35° and 145° are considered good. If the control distribution shows as poor, move the instrument toward the middle of your control or pick different points. On a rectangular deck, control near each corner is a practical starting point.

While you are in setup, turn on Prompt for Setup Checks and set a check interval. On a one-person crew nobody else is watching the tripod, so a timed reminder to re-check is cheap insurance. Our iCON Setup Anywhere video shows this setup on the tablet.

Step 3: Lock on and let the robot follow you

Once the station is set, lock the instrument onto your prism (the LOCK key on the iCR70/iCR80 starts a prism search and locks on). In continuous with lock mode, the instrument follows the prism as you walk and keeps measuring, so the tablet always shows where you are relative to the point.

  • Lost lock? Use PowerSearch (on instruments equipped with it) or the search function in the measure bar to find the prism again.
  • Busy site with reflective clutter? With an AP20, PowerSearch uses the target ID and only locks onto the prism above the AP20, ignoring other reflective objects on site.
  • Uneven pole handling? AP20 tilt compensation lets you take a measurement with the pole tilted instead of fighting the bubble on every shot.

Step 4: Lay out points and lines

Open the Layout Points or Layout Lines app, select the item, and follow the guidance on the tablet to walk onto it. Mark it, store the measurement, and move to the next one. A stakeout list keeps you working in a logical order instead of hopping across the deck.

For overhead work, Auto Staking is where a robotic instrument really pays off. Aim the telescope at the ceiling or floor, select the point and tap Start. The instrument measures, turns to the design X and Y on the actual surface, and switches on its laser pointer at the location once it is within tolerance. A helper on a lift just marks the dot. Using a stakeout list, you can run through a whole set of hanger or sleeve points this way. Stake to Wall does the same on a vertical surface, which is useful for penetrations.

Step 5: Back-check before you leave

Before you start and before you pack up, measure a known point or grid location and compare it with its coordinates. This confirms the setup still matches the building. The Checks app can also measure distances, angles and areas between laid-out points, so you can confirm spacing on a bolt pattern before concrete is placed.

When one-person layout is not the right call

We would rather tell you up front:

  • Poor control. If you cannot see enough well-distributed control from the work area, a robot cannot make up for it. Fix the control first.
  • Open sites with good sky. For earthwork and site layout over large areas, a GNSS rover such as the iCON GPS 70 T may be faster, as long as the accuracy requirement allows it.
  • Heavy traffic through the line of sight. Constant interruptions mean constant re-locking. A second person, or a different setup location, can be more efficient.
  • Brand new crews. The workflow is simple once it is learned, but the first project goes much better with training on your own instrument and files.

Rent first, or buy

If you want to try one-person layout on a live project, Datum rents iCON robots and tablets by the 2-day, weekly or monthly term (list rental rates as of 2026; availability is confirmed before quoting):

Rental 2-day Weekly Monthly
iCON robot 70 (iCR75) $500 $1,200 $3,200
iCON robot 80 (iCR82/iCR85) $600 $1,400 $3,500
CC80 tablet kit $100 $235 $700
AP20 AutoPole package $250 $500 $1,500

See the full list in our rental equipment catalog. Rental spend can often be applied toward a purchase. Datum also runs on-site total station training on your instruments and real project files, and the iCON file preparation guides are available on that page.

FAQ

Can one person really do layout with a robotic total station?

Yes. The instrument tracks the prism and measures on its own, so the operator only needs to walk to each point and mark it. Overhead work may still need someone on a lift.

How many control points do I need?

Setup Anywhere needs at least two, but more well-spread points give a stronger, checkable solution. Plan for control that surrounds the work area.

Do I need an AP20?

No, but on busy sites it reduces locking onto the wrong reflection and speeds up shots with tilt compensation and automatic pole height.

Get set up for one-person layout

Browse our robotic total stations and tell us about your work. Datum will build an exact quote for the instrument, controller and accessories you need. Contact Datum to get started.

Our favorite products featured in this blog

Example product title

3D Laser Scanner Price Guide: BLK360, RTC and ScanStation Packages
RTC300 vs RTC500 vs RTC700: How Leica's New RTC Scanners Differ
Total Station Price Guide: Manual, Robotic and GPS Compared